Willows at Bellevue![]() Project Update Construction Costs $8,398,778 Year of Completion 2008 Contract Amount $5.7 million Architect Coger/Shambarger Architects, Inc. Challenges Exceptionally difficult site conditions
caused by poor local drainage and
a high water table led to unstable
soil conditions during construction.
An aggressive schedule needed to
be managed under severe winter
conditions. Regardless of these and
other challenges the facility was
turned over to the owner 45 days
ahead of schedule. Total Square Footage 52000 Square Foot Cost $88.00 Number of Beds 90 bed Skilled Nursing/Assisted Living/Memory Care Facility |