Primrose ALF & ILF

Project Update
Construction Costs
$8,191,736
Year of Completion
2007
Contract Amount
$8.2 Million
Architect
WAI/Continuum
Challenges
Initial poor site drainage created major obstacles early on in site development; coupled with a two month delay in civil drawings, things started sluggishly and were slow to pick up speed. Constant changes in the city’s drainage and erosion control requirements further delayed progress. Unique material selections caused sequencing of construction to be rethought. In spite of these challenges the new building was turned over nearly 60 days ahead of schedule!
Total Square Footage
90000
Number of Beds
68 bed Independent Living and Assisted Living Facility
Project Type
Independent Senior & Assisted Living