Fountain View of Monroe

Construction Costs
$7,250,000
Year of Completion
2007
Contract Amount
$7.25 Million
Architect
Coger/Shambarger Architects, Inc.
Challenges
Midstream changes in state health department regulations forced quick redesign of certain systems. Late selection of finishes by interior designer delayed schedule acceleration. The project began with only one day between a signed contract and FIDS expiration date. Removal of existing structures on the construction site and heavily wooded areas on half the site caused for a slower than usual start. After all this, the project was still finished six weeks ahead of schedule!
Total Square Footage
70000
Number of Beds
120 bed Skilled Nursing Facility
Project Type
Skilled Nursing Home