Fountain View of Monroe![]() Project Update Construction Costs $7,250,000 Year of Completion 2007 Contract Amount $7.25 Million Architect Coger/Shambarger Architects, Inc. Challenges Midstream changes in state health
department regulations forced quick
redesign of certain systems. Late selection
of finishes by interior designer delayed
schedule acceleration. The project began
with only one day between a signed contract
and FIDS expiration date. Removal of
existing structures on the construction site
and heavily wooded areas on half the site
caused for a slower than usual start. After
all this, the project was still finished six
weeks ahead of schedule! Total Square Footage 70000 Number of Beds 120 bed Skilled Nursing Facility Project Type Skilled Nursing Home |