Golden Years Nursing Center

Project Update
Construction Costs
$3,056,068
Year of Completion
2005
Contract Amount
$3.1 Million
Architect
ML Architects & Planners
Challenges
A winter start, with well above average moisture, combined with an adjacent pond leaching into the site, creating the need to “de-muck” the entire site. An additional requirement for construction, was a fully self-contained waste water treatment plant.
Total Square Footage
25673
Number of Beds
50 bed Skilled Nursing Facility
Project Type
Skilled Nursing Home