Switchgear Demand Craziness!!!

Behind the critical milestones of building dry-in and completion of drywall hanging, the date of permanent power provides a key indicator of a project’s schedule trajectory towards completion. Unfortunately, the current construction industry is being severely impacted by major challenges within the electrical gear industry driven by demand, labor issues, and electrical component shortages. Critical switchgear components such as switchboards, distribution panels, and heavy-duty circuit breakers have historically taken four to six months to receive. Over the past year, lead times on these items have increased to a minimum of 12 months, and quoted lead times of 14-18 months are becoming the standard.

So how does this impact the construction industry? For comparison, a $25 million senior living project with a construction schedule of 18 months, would typically require permanent power to be in operation by the twelfth month of construction to allow the startup-up of essential HVAC equipment, building systems,...

Read More >